Somerset Sanitary Sewer Improvements Project
Phase 1A Contractor Update – August 17th - September 4th
The following activities are planned for the upcoming two-week period:
- Open Cut – Crew 1
- Cannell Drive – Upper Section: Crew 1 will finish this week by completing the open cut gravity sewer to Manhole 260, including all associated laterals.
- Cannell Drive – Lower Section: Beginning Monday, Crew 1 will start at Manhole 650 at the bottom of Cannell Drive and complete the open cut gravity sewer to Manhole 267, including all associated laterals.
- Open Cut – Crew 2 (Three-Week Look Ahead)
- Dott Avenue / Tayman Avenue: Crew 2 will finish this week and continue through Tuesday with the open cut gravity sewer installation from Manhole 59B to Manhole 45, located on Tayman Avenue.
- Dott Avenue / West Race Street: Crew 2 will then move to Manhole 49 on Dott Avenue and complete the open cut gravity sewer to Manhole 55A on West Race Street, including all associated laterals.
- This work will conclude Crew 2's three-week look ahead.
- Open Cut – Crew 3
- Vannear Avenue: Currently setting Manhole 90 and completing the open cut gravity sewer to Manhole 90A.
- Brubaker Street: Set Manhole 32A and Manhole 78, and complete the open cut gravity sewer to Manhole 78A.
- West Main Street / Tayman Avenue: Crew 3 will then set Manhole 85 on West Main Street and Manhole 87 on Tayman Avenue.
- Seed & Mulch Restoration
- The restoration crew is currently working in the Brierwood and South Edgewood areas, weather permitting.
- Blacktop Paving
- The paving crew is currently working on Terrilin Drive.
- The crew will then move to the Brierwood “change order work”, beginning with preparation work followed by base paving.
- This work will also include the associated section of Maplehurst Drive.
- Mainline Lining
- Mainline lining is currently on hold until additional work is completed, and sufficient areas are ready for lining operations to resume.
- Lateral Lining
- Lateral lining is currently underway on West Race Street and South Franklin Avenue.
- Next week, lateral lining operations will move to West Garrett Avenue.
Schedule Disclaimer
This construction schedule is provided for informational purposes only and is subject to change without notice. Actual work dates, locations, and activities may be adjusted due to weather, field conditions, utility conflicts, contractor operations, material availability, or other unforeseen circumstances. The Borough of Somerset will make reasonable efforts to provide updated information as changes occur.
Phase 1B Sewer System Improvements Contractor Update
Schedule date: August 17, 2026 Program: Street-by-Street Sewer Lining & Replacement Locations listed: 25
Street / Location |
Work Window |
Test Pit |
Planned Work |
S KIMBERLY AVE |
Aug 17 – Sep 15, 2026 |
Aug 17, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
E GARRETT ST |
Aug 18 – Sep 15, 2026 |
Aug 18, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
E SANNER ST |
Aug 19 – Sep 21, 2026 |
Aug 19, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- Catch Basin / Storm Line Install
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
ANKENY AVE |
Aug 20 – Sep 16, 2026 |
Aug 20, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
W RACE ST |
Aug 21 – Sep 23, 2026 |
Aug 21, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- Catch Basin / Storm Line Install
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
S CENTER AVE |
Aug 24 – Sep 21, 2026 |
Aug 24, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
S EDGEWOOD AVE |
Aug 25 – Sep 23, 2026 |
Aug 25, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
JONES ALLEY |
Aug 26 – Sep 22, 2026 |
Aug 26, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
W SANNER ST |
Aug 27 – Sep 23, 2026 |
Aug 27, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
W CHURCH ST |
Aug 3 – Sep 28, 2026 |
Aug 28, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- Catch Basin / Storm Line Install
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
W PATRIOT ST |
Aug 31 – Sep 25, 2026 |
Aug 31, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- Catch Basin / Storm Line Install
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
S COLUMBIA AVE |
Sep 1–23, 2026 |
Sep 1, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- Catch Basin / Storm Line Install
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
S ROSINA AVE |
Sep 2–30, 2026 |
Sep 2, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
BERKEY ST |
Sep 3–29, 2026 |
Sep 3, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
E CHURCH ST |
Sep 4–29, 2026 |
Sep 4, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
E MAIN ST |
Sep 7–24, 2026 |
Sep 7, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
E PATRIOT ST |
Sep 8 – Oct 6, 2026 |
Sep 8, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
W MAIN ST |
Sep 9 – Oct 5, 2026 |
Sep 9, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
LOUTHER ST |
Sep 10 – Oct 6, 2026 |
Sep 10, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
FRANKLIN AVE |
Sep 11 – Oct 8, 2026 |
Sep 11, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- Catch Basin / Storm Line Install
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, As Needed)
- Grass/Concrete/Paving Restoration
|
UNION ST |
Sep 14 – Oct 5, 2026 |
Sep 14, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- Catch Basin / Storm Line Install
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
FAIRVIEW ST |
Sep 15 – Oct 13, 2026 |
Sep 15, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
Source schedule note: Street summary finishes 10/13/26, while the listed Grass/Concrete/Paving Restoration activity finishes 10/6/26. |
COLBY AVE |
Sep 16 – Oct 7, 2026 |
Sep 16, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
ROW of UNION ST |
Sep 17 – Oct 7, 2026 |
Sep 17, 2026 |
- Test Pit
- Traffic Control Setup & Lane Closures
- Sewer Cleaning & Pre-Lining CCTV Inspection
- Manhole/Sewer Line Replacement
- Manhole Frame & Lid Replacement
- CIPP Lining Installation & Cure
- Sewer Lateral Replacement (Open-Cut, Lining)
- Grass/Concrete/Paving Restoration
|
Schedule Disclaimer
This construction schedule is provided for informational purposes only and is subject to change without notice. Actual work dates, locations, and activities may be adjusted due to weather, field conditions, utility conflicts, contractor operations, material availability, or other unforeseen circumstances. The Borough of Somerset will make reasonable efforts to provide updated information as changes occur.
What Residents Can Expect
- Active excavation within designated work zones
- Temporary traffic adjustments or lane restrictions
- Possible short-term driveway access interruptions during lateral installation
- Temporary surface restoration following sewer installation
Crews will work to minimize disruption and restore affected areas as quickly as possible once underground work is completed.
For questions regarding construction activities, please contact the Borough office (814) 443-2661.
Thank you for your patience as we work to improve local infrastructure.
PROJECT OVERVIEW

The Somerset Borough Municipal Authority is conducting a major Sanitary Sewer Improvements Project required by regulations to eliminate it’s hydraulically overloaded condition. This initiative began in 2016 and is scheduled for completion in 2032. The project addresses hydraulic overload conditions caused by excess Infiltration and Inflow.

Key Terms and Definitions
- Hydraulic Overload: Occurs when wastewater and/or extraneous water exceed the physical capacity of the wastewater system.
- Wastewater: Domestic sewage or industrial process water.
- Extraneous Water (I&I): Groundwater or stormwater that enters the wastewater system through leaks or improper connections.

Causes and Prevention of I&I
I&I is introduced through cracked or defective pipes, improper stormwater connections, and non-watertight infrastructure. I&I is prohibited from intentionally being directed into the Authority’s wastewater system. To combat this, the Authority plans to replace and repairs pipes, disconnects improper stormwater links, and installs watertight materials.

Project Phases
- Phase 1 – Collection System: Foc sewer laterals, mains, and manholes, and includes stormwater improvements.
- Phase 2 – Wastewater Treatment Plant & Flow Equalization: Expands treatment and equalization capacity.
- Phase 3 – Interceptor Sewers and Pumping Stations: Improves large conveyance lines and pumping facilities.
Estimated Construction Schedule
Phase |
Area |
Schedule |
1A |
Brierwood & West Somerset |
Oct 2025 – Dec 2026 |
1B |
Central Business District |
Jun 2026 – Sep 2027 |
1C |
East Somerset |
Sep 2026 – Dec 2027 |
1D |
North Somerset |
Apr 2027 – Dec 2028 |
| Flow |
Post Construction Flow Monitoring |
Nov 2028 - May 30 |
2A |
WWTP & Equalization |
Dec 2030 – Jun 2033 |
2B |
WWTP & Equalization |
Dec 2032 – Dec 2034 |
3A |
Interceptors & Pumping Stations |
June 2033 – May 2035 |
3B |
Interceptors & Pumping Stations |
Mar 2034 – Mar 2036 |
Property Owner Information
Most construction will occur within public roadways, but some sewer connections reach private properties. Property owners are responsible for maintaining their sewer lateral up to the sewer main. If an easement is required, the Authority will contact property owners with detailed agreements. After the construction of a viewport through this project, the property owners will be responsible for maintaining their sewer lateral from their building up to the viewport/property clean-out.

Project Updates and Communication
The Authority will share updates via the Borough’s website, social media, and water/sewer bills. Residents are encouraged to check periodically for new information and contact the Borough office with any questions. You can utilize the following link to view live updates on the construction progress. View Construction Progress