PAY MY BILL    | COUNCIL PORTAL | MUNICIPAL AUTHORITY PORTAL
Leaks and Projects

Projects

 

Somerset Sanitary Sewer Improvements Project


Phase 1A Contractor Update – August 17th - September 4th

The following activities are planned for the upcoming two-week period:

WEEK 1
  • Crew 1
    • Install open cut 18” storm S. Edgewood
    •  Install open cut 15” gravity sewer S. Edgewood
  • Crew 2
    •  Install open cut 8” gravity sewer Smith St.
  •  Crew 3
    • Install viewports on Circle Dr.
    •  Open cut laterals on Smith St.
  • Paving Crew
    • Continuing to pave into the Brierwood and W. Somerset areas.
      • Note: paving locations can be sporadic due to weather conditions and opportunities
  • Restoration Crew
    • Continuing restoration efforts in the Brierwood and W. Somerset areas.
      • Note: restoration locations can be sporadic due to weather conditions and opportunities.
  • Mainline Lining Crew
    • Mainline rehabilitation will be continuing Monday 9/28 & Tuesday 9/29
      • MH 88 to MH 87 (Tayman Ave.)
      • MH 37 to MH 36 (Smith & W. Main Right-of-Way)
      • MH 266 to MH 267 (Cannell Dr.)
  • Lateral Lining Crew
    • Monday, September 28, 2026: 32 to 32A Brubaker (1) lateral; 99 to 100 Vannear (1) lateral; 5 MH W Race Tank Shot; prep 58 to 59A.
    • Tuesday, September 29, 2026: 58 to 59A W Somerset quantity (5) laterals, prep W Main reinstatements.
    • Wednesday, September 30, 2026 - MH 34 to 35 W Main quantity (6) laterals.
    • Thursday, October 1, 2026 - MH 34 to 35 W Main (1) lateral; MH 34 to 33 W Main (1) lateral; clean 815 and 817 W Garrett.
WEEK 2
  • Crew 1
    • Complete Field Order 3 on Vannear Ave.
  • Crew 2
    • Complete Field Order 4 on S. Franklin Ave.
  • Crew 3
    • Continuing open cut laterals on Smith St.
    • Install manhole 41A in ROW of Tayman Ave. to Smith St.
  • Crew 4
    • Install viewports and open cut laterals ROW between Cannell Dr. and Maplehurst Dr.
      • C-1.07 - MH 599 to MH 598 (Brierwood Right-of-way)
    • Continue viewports and open cut laterals ROW between Cannell Dr. and Maplehurst Dr.
      • C-1.05 & C-1.07 - MH 600 to MH 601 (Brierwood Right-of-way)
  • Paving Crew
    • Continuing to pave into the Brierwood and W. Somerset areas.
      • Note: paving locations can be sporadic due to weather conditions and opportunities
  • Restoration Crew
    • Continuing restoration efforts in the Brierwood and W. Somerset areas.
      • Note: restoration locations can be sporadic due to weather conditions and opportunities.
  • Mainline Lining Crew
    • No work predicted at this time. (We will be installing mainline liner for the Phase 1B project.
  • Lateral Lining Crew
    • Monday, October 5, 2026 - MH 79 to 80 quantity (5) laterals.
    • Tuesday, October 6, 2026 - MH 80 to 83 W Main quantity (5) laterals.
    • Wednesday, October 7, 2026 - MH 93 to 92 Circle Dr quantity (2) laterals, and MH 42 to 43 Davis (1) lateral.
    • Thursday, October 8, 2026 - MH 99 to 90 Vannear (1) lateral.

Schedule Disclaimer
This construction schedule is provided for informational purposes only and is subject to change without notice. Actual work dates, locations, and activities may be adjusted due to weather, field conditions, utility conflicts, contractor operations, material availability, or other unforeseen circumstances. The Borough of Somerset will make reasonable efforts to provide updated information as changes occur.

Phase 1B Sewer System Improvements Contractor Update

Week 9/28 - 10/1 We will be completing open cut on Ice Street and Kimberly, and misc. traffic pattern changes for camera work on Main, Patriot, Edgewood, etc.

 

Schedule Disclaimer
This construction schedule is provided for informational purposes only and is subject to change without notice. Actual work dates, locations, and activities may be adjusted due to weather, field conditions, utility conflicts, contractor operations, material availability, or other unforeseen circumstances. The Borough of Somerset will make reasonable efforts to provide updated information as changes occur.


What Residents Can Expect
  • Active excavation within designated work zones
  • Temporary traffic adjustments or lane restrictions
  • Possible short-term driveway access interruptions during lateral installation
  • Temporary surface restoration following sewer installation

Crews will work to minimize disruption and restore affected areas as quickly as possible once underground work is completed.
For questions regarding construction activities, please contact the Borough office (814) 443-2661.

Thank you for your patience as we work to improve local infrastructure.

 PROJECT OVERVIEW

Placeholder image

The Somerset Borough Municipal Authority is conducting a major Sanitary Sewer Improvements Project required by regulations to eliminate it’s hydraulically overloaded condition. This initiative began in 2016 and is scheduled for completion in 2032. The project addresses hydraulic overload conditions caused by excess Infiltration and Inflow.

Infiltration and Inflow image

Key Terms and Definitions
  • Hydraulic Overload: Occurs when wastewater and/or extraneous water exceed the physical capacity of the wastewater system.
  • Wastewater: Domestic sewage or industrial process water.
  • Extraneous Water (I&I): Groundwater or stormwater that enters the wastewater system through leaks or improper connections.

Causes and Prevention image

 Causes and Prevention of I&I

 I&I is introduced through cracked or defective pipes, improper stormwater connections, and non-watertight infrastructure. I&I is prohibited from intentionally being directed into the Authority’s wastewater system. To combat this, the Authority plans to replace and repairs pipes, disconnects improper stormwater links, and installs watertight materials.

Causes and Prevention of I&I image

 Project Phases
  1. Phase 1 – Collection System: Foc sewer laterals, mains, and manholes, and includes stormwater improvements. 
  2. Phase 2 – Wastewater Treatment Plant & Flow Equalization: Expands treatment and equalization capacity. 
  3. Phase 3 – Interceptor Sewers and Pumping Stations: Improves large conveyance lines and pumping facilities.
 Estimated Construction Schedule

Phase

Area

Schedule

1A

Brierwood & West Somerset

Oct 2025 – Dec 2026

1B

Central Business District

Jun 2026 – Sep 2027

1C

East Somerset

Sep 2026 – Dec 2027

1D

North Somerset

Apr 2027 – Dec 2028

Flow Post Construction Flow Monitoring Nov 2028 - May 30

2A

WWTP & Equalization

Dec 2030 – Jun 2033

2B

WWTP & Equalization

Dec 2032 – Dec 2034

3A

Interceptors & Pumping Stations

June 2033 – May 2035

3B

Interceptors & Pumping Stations

Mar 2034 – Mar 2036

 

Property Owner Information

Most construction will occur within public roadways, but some sewer connections reach private properties. Property owners are responsible for maintaining their sewer lateral up to the sewer main. If an easement is required, the Authority will contact property owners with detailed agreements.  After the construction of a viewport through this project, the property owners will be responsible for maintaining their sewer lateral from their building up to the viewport/property clean-out.

Property Owner Information image

Project Updates and Communication

The Authority will share updates via the Borough’s website, social media, and water/sewer bills. Residents are encouraged to check periodically for new information and contact the Borough office with any questions. You can utilize the following link to view live updates on the construction progress.  View Construction Progress